Types of Building Lime
|
||||
Natural Hydraulic Lime (NHL) Powder lime binder for mixing with sand
|
||||
Lime putty (Calcium hydroxide) Traditional form of lime that sets once dry
|
||||
Quicklime (Calcium Oxide) The reactive raw material use for making lime putty
|
||||
Formulated lime What is it?
|
||||
Hydraulic lime A little different than natural hydraulic lime
|
||||
Hydrated lime Builders bagged lime additive
|
||||
Working with Natural Hydraulic Lime
|
||||
Setting times How long will your lime take to set and cure?
|
||||
Mixing NHL mortars Relatively straight forward but needs to be correct
|
||||
When to add hair to lime mortars Important addition for some work
|
||||
Pointing with lime mortar Select the correct lime mortar and employ correct techniques
|
||||
Rendering with hydraulic lime Find an example specification for rendering with NHL mortar
|
||||
Bedding with NHL Building a wall? Find out the techniques and mixes to use.
|
||||
Painting hydraulic lime Using compatible paints with lime products, here are some options
|
||||
What is lime plaster? How is this defined and which mix to use? | ||||
What is limewash? Used for thousands of years, we take the mystery out of limewash | ||||
Storing hydraulic limes Hydraulic limes have limited life, if stored well, this limit is extended
|
||||
Training courses Learn both theory and practical on our one day courses
|
||||
Limecrete A flexible and breathable floor can be important for traditional buildings
|
||||
Other stuff
|
||||
Insulating lime renders Why not consider reducing your heating bills when rendering or plastering?
|
||||
Why use lime on old buildings? Here are some compelling reasons to use lime
|
||||
What is wrong with cement mortar? Here are some compelling reasons not to use cement
|
||||
When should I use lime putty and when should I use NHL? Confused? Read this section | ||||
What is slaking? An important process and a common term explained
|
||||
Pozzolans Making fat limes hydraulic, the Roman way | ||||
Harling coat, scat or splatter dash Whatever you call it, this is essential for many applications
|
||||
How much does hydraulic lime cost? Find out the best value brands and how to purchase it. |
Natural Hydraulic Lime (NHL)
Natural hydraulic lime (or NHL) comes from limestone that has natural impurities of clay and other minerals, the amount of impurities within it determines how hard it will set.
Natural hydraulic lime sets with water (rather than with air as with lime putty) hence the term ‘hydraulic’.
Natural hydraulic lime powders come in 3 European grades:
Grade | Conpressive Strength (MPa) @ 28 days | Examples of Use | |
NHL2 | >2 to <7 | Pointing internally or with soft masonry, plastering | |
NHL3.5 | >3.5 to <10 | Bedding, pointing | |
NHL5 | >5 to <15 | Flooring, below DPC or chimney flaunchings |
Natural hydraulic lime can be used when speed is essential as it sets much quicker than a lime putty mortar.
Natural hydraulic lime is less flexible and less vapour permeable (breathable) than a lime putty mortar.
The ratio of sand to binder varies depending on what job you are doing. A 3:1 mix may be used for pointing of top coat renders, but for floor screeds a stronger 2:1 mix would be used.
Hydraulic lime
Hydraulic lime (HL) consists of lime and other materials such as cement, blast furnace slag, limestone filler or other materials that change the properties of the binder. The additives do not have to be declared which is legally different to natural hydraulic lime.
Formulated lime
Formulated lime (FL) consists of hydrated lime and/or natural hydraulic lime with added hydraulic or pozzolanic material. Inclusion of any cement or cement clinker must be declared and at a limited percentage. This is legally different to a natural hydraulic lime and formulated lime.
Lime putty
Lime putty as a binder has been used for thousands of years. It has many names, such as non-hydraulic lime, fat lime or air lime, which often causes confusion.
Lime putty is made when quicklime is mixed (slaked) with water and left to mature for a minimum 3 months until in solidifies.
Lime Putty cures by carbonation with the air (at a rate of approximately 1 mm per month) and can therefore be kept for many years in an air tight environment. Lime putty also improves with age.
Hydrated Lime
Hydrated lime is often confused with natural hydraulic lime due to them having similar names and supplied as a powder but is not to be used for the same applications. Hydrated lime is created when quicklime is added to a small amount of water whilst still retaining it’s solid state.
Hydrated lime is usually used as an additive in cement as a plasticiser and it should not be used as a binder in its own right.
Quicklime
Quicklime (calcium oxide) is the raw material that is used to make lime putty. It is made by burning limestone or chalk in a kiln resulting in a highly reactive material. Quicklime is available in a range of sizes from lumps down to very fine powder.
Hydraulic Lime Mortar (HLM) with Applications
Please use the following tables to assist with strength and mix ratios relevant to the job at hand:
Building element
|
Hydraulic Lime Mortar Designation
|
Internal walls | HLM 0.5 |
External walls | HLM 0.5 – 2.5 |
Facing to solid construction | HLM 1.0 – 2.5 |
Walls close to/below ground | HLM 2.5 – 3.5 |
Parapets, sills, lintels and cornices | HLM 2.5 – 3.5 |
Copings and cappings | HLM 2.5 – 5.0 |
Chimneys | HLM 3.5 – 5.0 |
Earth retaining walls | HLM 3.5 – 5.0 |
Masonry below water level | HLM 5.0 |
HLM Designation
|
NHL2 lime:sand by volume | NHL3.5 lime:sand by volume | NHL5 lime:sand by volume |
Mean compressive strength (MPa@91 days)
|
HLM 5 |
–
|
–
|
1:2
|
5.0
|
HLM 3.5 |
–
|
–
|
1:2.5
|
3.5
|
HLM 2.5 |
–
|
1:2
|
1:3
|
2.5
|
HLM 1 |
1:2
|
1:3
|
–
|
1.0
|
HLM 0.5 |
1:3
|
–
|
–
|
0.5
|
Mixing Natural Hydraulic Lime Mortar
It is essential that lime is uniformly dispersed and that any fine agglomerations are broken down. The time of mixing will be controlled by the efficiency of the mixer. Roller-pan mixers and screed mixers have the most efficient action but simple tilting-drum cement mortar mixers can be used if a longer mixing time is allowed. If the job is sufficiently large use a mixer with a capacity for a full bag of lime.
The following sequence will be suitable for a tilting-drum mixer.
- When mixing wear protective goggles and waterproof gloves.
- Introduce half of the sand and add all of the lime, mix well for 2 to 5 minutes until a uniform colour is achieved.
- Stop the mixer and isolate the drive. Scrape down any material adhering to the back. Add the remaining sand and mix again for 2 to 5 minutes to get uniform dispersion.
- Continue mixing adding water slowly over at least 10 minutes and giving plenty of time for water to be fully incorporated. The mortar should be more like a dough than a slurry and the less water added to achieve this, the better the mortar performance will be.
- The longer the final mixing time the more workable (fatter) the mortar will be. Workability will be improved by allowing mixed mortar to stand for 15 minutes or longer before re-mixing for a further 5 minutes (in hot weather do not over-mix as water will be lost through evaporation).
Additions
Gauging hydraulic limes is not normally required although addition of pozzolanic materials can improve the hydraulic activity and performance in some applications. Materials such as used crushed brick, fly ash, ground granulated blast furnace slag (GGBS) or metakaolin (Argical) may be used to increase the mortar strength designation.
The addition of hydrated lime or lime putty can improve the plasticity but may reduce the mortar strength designation.
It is recommended that trial mixes be produced to establish the optimum properties for a particular application.
Pointing with Lime Mortar Click here for a lime pointing pdf guide
Carefully choose which lime is most appropriate for the situation, selecting a weaker mix for softer masonry.
If not purchasing a premixed mortar then ensure you select the correct sands for texture and colour as required.
Generally, NHL 2 or lime putty mortar for internal use, and either NHL 3.5 or lime putty mortar plus pozzolan is recommended externally.
Preparation
Any existing defective pointing must be raked out to a depth usually equal to twice the width of the joint, but generally not less than 20 mm. The back of the joint should be roughly square in profile. Plugging chisels ensure that the stone or bricks aren’t forced apart. Never use an angle grinder or similar type of equipment which may damage the masonry.
Damping
The joints must be dampened with enough time left for the stone or brick faces to dry to prevent smearing. The mortar should be as dry as it is practicable to point with. This allows maximum compaction in the joint, reduces shrinkage cracking and reduces the tendency to smear on the stone faces.
Premixing
Lime mortars benefit from being premixed before use. Allow 30 minutes for a natural hydraulic lime mortar compared to up to a week for lime putty mortar. Pre-mixing is obviously unnecessary when purchased as a ready to use mortar.
When you’re ready to carry out the work, the mortar is “knocked up” (agitated/mixed) immediately prior to use to plasticise the mix and help to reduce shrinkage. Any pozzolan additive should be mixed in at the final knocking-up stage and not before.
Selecting the mortar
It is very important to select the correct grade of natural hydraulic lime and then mix the correct ratio of sand to lime in order that the strength and vapour permeability is appropriate for the masonry.
Pointing
Start at the top of a wall to allow for cleaning up and spraying to continue. Use a pointing spatula/small tool and push the mortar in from a hawk.
Joints deeper than 20 mm may need an initial dubbing out as shrinkage can occur otherwise.
Finish flush or rebate a little if the joints have widened with age or for personal preference as rebating highlights the stone more (weather striking).
Brushing
When the mortar is “green hard” (firm enough to brush without smearing but still malleable enough to work) brush or tamp the joints with a churn brush to enhance the aggregate and give a coarser texture to the pointing. During this process, it is possible to throw a dry indigenous soil at the soft lime mortar to pre-weather and allow it to blend in to the wall as a fresh, bright lime mortar is not always desirable.
Protection
External pointing should be mist sprayed to control drying and protected from direct sun and wind. In winter it should be protected from rain and frost. Hessian cloth is recommended.
Quantities
20 kg of lime putty mortar will point 2-3 m² of average sized stonework or 1- 1.5 m² of brickwork based on a 10 mm joint and 20 mm depth.
Time of year
Great care should be taken not to apply lime mortars too late in the year or too soon in spring to avoid damage from frost. The ultimate hardening process takes up to a month for each millimetre of thickness. Therefore it could take 20 months before mortar has carbonated to a depth of 20 mm.
It is recommended that trial mixes be produced to establish the optimum properties for a particular application.
Safety
Limes are caustic. Always wear eye protection and protective gloves and clothing and follow the safety instructions on the labels.
Please contact us full more guidance and information.
Rendering with Natural Hydraulic Lime
- Harling Trowel
- Harling Application
- Scratch Coat
- Scratch Comb
- Float Coat Application
- Wood Float Finish
The following is an example of a rendering specification that could be suitable for many situations but please ensure that it is suitable for your own particular project:
1. Ensure that appropriate scaffolding is in place and the worksite safe for workers and public.
2. Take off the existing render, except any existing sound lime mortars, taking care not to damage the structure. Look out for very thick patches of render that are effectively load bearing. It may be preferable to render on top rather than risk rebuilding an area.
3. Dub out any deep holes in the wall with a haired lime mortar, rebuilding defects with cob blocks, bricks or stone as appropriate.
4. Treat wooden lintels with preservative and counter batten with oak lath if rendering over them.
5. Apply one hand harled coat of Secil Consolidation Mortar to provide a key to the wall.
6. Apply sufficient coats of haired mortar to smooth the contours of the wall. With a suitable animal hair in the mortar coats can be applied up to 12-15 mm thick. The hair reduces any slumping whilst applying and shrinkage cracking whilst curing. Each backing is keyed with a scratch comb. The mortar should be NHL3.5 mixed to a ratio of around 2.5:1 of lime/sand.
Each subsequent coat should be a weaker mix or thinner than the previous coat to encourage moisture to be drawn out of the wall.
7. Apply a top coat of floated or hand harled lime mortar as desired. The mix should be NHL3.5 mixed at 2.5:1 or 3:1 with sand and applied at 6-8 mm for a float coat or 3 mm for a harled coat.
Damping & curing
It is very important to control suction from the wall by light spraying with water half an hour before applying each coat (especially cob and porous brick) and in warm weather it will be necessary to spray each coat afterwards. Whatever the season, protect each render coat during the curing process from all the elements such as hot drying wind, strong sun, rain and don’t apply in temperatures below 5 degrees centigrade or if there’s a risk of frost. A heavy cloth such as hessian sheeting will provide a suitable physical barrier and should be left in place as long as required.
Curing
All coats need to be given at least a few days to harden before subsequent coats are applied. To test whether a coat is ‘green hard’ the surface should be resistant to a fingernail.
Many factors will influence the timing such as the season, exposure of wall and the thickness of the coat but it’s normal to expect a couple of days for the harled coat to harden and perhaps 4- 7 days for each of the thicker coats.
Quantities
For the example specification per m²:
- 3 mm scat coat of NHL3.5 unhaired mortar at 2:1 = 6 kg/m²
- 15 mm scratch coat of NHL3.5 haired mortar at 2.5:1 = 30 kg/m²
- 7 mm floated top coat of NHL3.5 unhaired mortar at 2.5:1 = 14 kg/m² or repeat the first scat coat for a rough cast finish.
Time of year
Please note that great care should be taken not to be applied too late in the year or too soon in spring or else frost damage may occur. It is important to prevent frost crystals forming within the mortar soon after application. The ultimate hardening process takes up to a month for each millimetre of thickness. Therefore it may take 20 months before mortar has carbonated to a depth of 20 mm.
Training
We offer a one day practical course in using lime in renovation and we also sell a training DVD based on the course.
Safety
Limes are caustic. Always wear eye protection and protective gloves and clothing and follow the safety instructions on the labels.
Please contact us full more guidance and information.
Bedding/Rebuilding in Stone with Natural Hydraulic Lime
Rebuilding and repairing with lime mortars offers a number of advantages:
- They match the existing structure for porosity and density, allowing moisture to move in a similar way.
- They can accommodate general movement better than a hard mortar.
- Soluble salts will be less likely to crystallise in the stone or brick faces.
- They match existing walls aesthetically.
Before starting any work, always check if building is listed. If it is listed, contact your local Conservation Officer to discuss the project.
Preparation
Try to select stone from a local quarry to match the existing. Take a sample along to the quarry if you’re not sure. You can usually get two size ranges; 4″-6″ and 6″ – 9″.
For the bedding mortar select an appropriate strength for your masonry, a regular mix would be NHL3.5 mixed at 1 part lime to 2.5 or 3 parts sharp wash pit sand. The sand should be a good blend of coarse and fine particles. The largest size particle is ideally about 1/3rd the thickness of the bed to be laid, so for a 10 mm bed, 3-4 mm is ideal.
Building
If you’re a novice, position a stone dry first to make sure it looks right and you have got the best face showing. Stagger the vertical joints so there isn’t a vertical joint running continuously up the wall.
Mixing
See mixing hydraulic lime section on this page. Natural hydraulic lime (NHL) benefits from premixing by an hour then mixing again just prior to use.
Application
Use a mortar bed just thick enough to spread the load evenly, finishing just beyond the front face and then trimming flush with the edge of the gauging trowel.
Use a through stone that can tie together the entire thickness of the wall or thereabouts, one every m² of wall face, pinning the wall together from both faces.
The mortar shouldn’t dry out too quickly – protect from sun, wind and rain with damp hessian cloth. Protect from rain if necessary.
Build up to a maximum of 1 metre high at a time and then let the lime mortar cure for 2 to 3 days. When ‘green hard’, the joints can be brushed with a stiff brush to expose the aggregate.
Time of year
Please note that great care should be taken not to be applied too late in the year or too soon in spring or else frost damage may occur. It is important to prevent frost crystals forming within the mortar soon after application. The ultimate hardening process takes up to a month for each millimetre of thickness. Therefore it may take 20 months before mortar has carbonated to a depth of 20 mm.
Safety
Limes are caustic. Always wear eye protection and protective gloves and clothing and follow the safety instructions on the labels.
Setting/curing times
Lime putty has to dry through suction from the substrate and evaporation before it can carbonate. Carbonation may take many years before fully completed and fully hardened. Any lime with hydraulic qualities, be it formulated, natural or ‘hydraulic’, will set in the presence of water and doesn’t need to dry before hardening.
All lime mortars benefit from protection from drying rapidly or frost crystals forming in them before fully cured. We recommend using hessian.
For curing to complete effectively, it is important that moisture is kept in any lime mix for at least 72 hours before being allowed to dry out slowly. Premature drying will result in a feeble mortar or plaster. Saturated substrate or low temperatures will result in extended curing times.
Repointing an old wall will usually result in rapid hardening due to the likely suction from old dry masonry and mortar and it may be difficult to keep it moist for as long as is ideal and can harden in a day or two. Pointing however, is not structural and will rarely be a major issue if weak and can be a positive asset as it helps to ensure that the pointing is weaker than the masonry, therefore protect the masonry by encouraging moisture egress via the pointing.
Bedding mortars may take a week or more to get significant strength.
Rendering and plastering layers are best applied onto ‘green hard’, recently applied coats as this controls the suction and helps create a good bond. If previous applications are allowed to fully dry, this can make application of new layers difficult to control and work. Our lightweight Secil ecoCORK insulating render can be applied on to previous layers more quickly than normal lime renders or lime plasters.
Example Build-ups and Timings
Internal Lime Plastering
|
|
Timing
|
Application
|
Day 1 | Scat/harled coat (if required) |
Day 2/3 | Scratch coat |
Day 10 | Float coat |
Day 14 | Skim coats |
Day 18-21 | Limewash coats x 4 (one coat per day) |
OR | |
day 28+ | other breathable paint finish |
External Lime Rendering
|
|
Timing
|
Application
|
Day 1 | Scat/harled coat – if required |
Day 2-3 | Scratch coat |
Day 10 | Float coat |
Days 17-20 | Limewash coats x 4 (one coat per day) |
OR | |
Day 24 | Silicate Primer |
Days 25-26 | Silicate Paint coats (one coat per day) |
External Lime Render with Secil ecoCORK
|
|
Timing
|
Application
|
Day 1 | Scat/harled coat |
Day 2/3 | ecoCORK coat with 4 mm fibre glass mesh |
Day 4/5 | additional ecoCORK coat (if required) |
Day 6/7 | Finishing render coat |
Day 21 | Silicate Primer |
Day 22-23 | Silicate Paint coats (one coat per day) |
Why Use Lime on Old Buildings?
Before this century building techniques and materials were very different from those employed today. Traditional properties need to “breathe” to allow moisture inherent in a solid wall construction without a damp proof course to evaporate from the external stonework or render.
Many old buildings are constructed from materials such as brick, cob and stone which are relatively porous and often of lower strength. Lime mortars were normally used for bedding and plastering. Lime mortar is a relatively softer mortar and therefore it is able to withstand a certain amount of movement (without cracking) that comes with settlement and seasonal changes in ground conditions.
Lime mortar is porous and allows moisture to evaporate, helping to keep a building free of damp.
What is Wrong with Cement Mortar?
Apart from the adverse effect it has on the environment in general, cement mortar is usually hard, brittle and less porous than lime mortar. It often contains additives to make it sometimes completely waterproof and is damaging to traditional buildings for several reasons.
Cement mortar is often harder than old bricks, cob or some types of stone, therefore when movement occurs it may damage these softer traditional construction materials. Hard cement mortar can trap moisture behind it causing damage to the structure and encourages ground water to rise up a solid wall by capillary action. Trapped water in the wall can cause poor insulation, decay and crumbling. In severe cases a cob wall can fail. The brick, cob or stone can also be subject to frost damage if moisture levels are to high.
When Should I Use a Natural Hydraulic Lime vs Lime Putty?
Natural hydraulic limes set even when wet and come in a range of strengths. They are useful for building with stone or brick where the earlier set may speed up construction. But you can also add a pozzolan to a lime putty mortar.
We suggest that for external bedding and pointing late in the year it would be better to use natural hydraulic lime. It is capable of a faster initial set in cold weather.
For most external rendering and internal plastering jobs, the fattiness of lime putty makes a superior mortar that allows coarser sands and thicker coats to be applied without shrinkage.
If the budget is very tight and there are no compelling practical reasons to go for lime putty then a natural hydraulic lime binder mixed with a carefully selected locally sourced sand invariably works out less expensive .
If you are a total novice to lime work, it is usually best to use a premixed product to minimise the potential issues that could arise. Premixed lime putty mortars/plasters have a long shelf life and need to be kept free from drying out until used.
Premixed hydraulic lime mortars (HLM) have a shelf life limited in part to how it is stored and needs to be kept dry until used.
What is Slaking?
Slaking is the process for making lime putty. Quicklime is added to water and a chemical reaction occurs resulting in the release of a large amount of heat from the quicklime creating a boiling liquid.
Chemically the calcium oxide is converted into calcium dihydroxide.
The longer the slaked lime is matured in the tank the better the lime putty. We leave ours for approximately 3 months before mixing with sands to create lime putty plasters and mortars.
What Sands are Suitable?
For lime putty mortars, the sand used for building, pointing and backing coats of render and plaster should be a washed sharp coarse sand. Use a sharp sand to BS882 which is free of vegetable matter, clay and salts.
While a NHL based mortar also requires a sharp, washed, well graded sand, the sand is often slightly less coarse than that used for a lime putty based mortar. You always need to be mindful when using less coarse sands that they may need to be applied in slightly thinner coats to avoid the risks of shrinkage cracks. For finishing coats of internal plaster use a very fine sand with the lime putty or NHL2.
How Long can Lime Mortar be Stored?
Premixed lime putty mortars can be stored for many months if sealed from the atmosphere and safe from frost in dumpy bags or sealed tubs.
Mortars with hair teased in will gradually lose the hair as it dissolves in an alkaline wet mortar and you will end up with an unhaired mortar.
Hydraulic lime mortars have a shelf life and should be stored dry and sealed from the atmosphere to prolong its life. If stored correctly, the bags of dry powder could last anything from 4-12 months from manufacture.
When Do I Add Hair to Lime Mortar?
Traditionally, some form of fibre was added to a lime mortar when applying it to the first application on to a lath wall or ceiling. For all other applications, the addition of fibres are optional and depend on the build-up and make-up of the plasters.
With NHL mortars we would suggest that 8-12 mm layers will require fibres and anything above 10 mm with lime putty. On to solid walls, it is acceptable to apply thinner coats without fibres.
Traditionally, animal hair such as horse, cow or goat, is added to the backing coats of lime render and plaster. In some instances, white goat hair can be found in the final skim coat.
Adding hair gives extra strength and minimises shrinking and cracking. It allows thicker coats to be applied to uneven walls and holds the plaster keys in place when plastering onto lath.
Painting Natural Hydraulic Lime
A lime mortar should not be painted with a modern paint laden with acrylic additives.
Externally, it is preferable to use a Silicate Masonry Paint.
Internally, the choice is far greater, for example: distemper, earthborn emulsion, Clay paint, limewash
What is Lime Plaster?
Lime plaster is the finishing plaster used as a final skim internally.
We supply two grades of lime plaster – Heritage Plaster and Regency Plaster.
Heritage Plaster is our standard and most popular lime skim. Regency Plaster is appropriate for matching the finest historic finishes and can also be used a filler for minor cracks.
If making your own lime plaster it is vital to source a suitable washed, kiln dried sand of 1 mm or less grain size. It is recommended to mix the lime putty and sand together at least two weeks before application to lessen shrinkage cracks. Sometimes a plaster is created by mixing NHL2 with sand. This needs to be used within a few hours of mixing with sand and water.
What is Limewash?
Limewash at it’s most basic is a traditional, breathable paint made from lime putty which is thinned with water.
Our limewash is approximately 1 part mature lime putty to 1 part water for optimum performance and minimal number of coats required.
Limewash can be coloured with pigments and can be used internally or externally on lime plaster, lime render, stone or brick. It works best on porous surfaces and hardens as it absorbs carbon dioxide from the atmosphere to form calcite crystals, giving it a unique appearance.
Typically four coats of limewash are needed on new external render and three coats on new lime plaster.
Limewash can be used inside or outside. Before making a decision on which paint to use, it is important to understand that limewash can be a little powdery if not applied well or on to a surface that isn’t suitable. Limewash can also have a non uniform colour due to differences in suction on the surface, this is usually due to differing moisture levels. The most obvious cause of this is rain hitting an external wall. Some people love this authentic appearance, some people loathe it. Be sure that you understand before application. Choose an suitable alternative if you don’t like the effects, in association with your Conservation Officer if the building is listed.
Click here for a full guide to applying limewash.
What is a Pozzolan?
A pozzolan is an additive that reacts with the lime in a mortar to create harder chemical set and so is very useful for damp or frost-prone environments. We use a metakaolin from burnt clay and advise it is used for most external work in strictly regulated amounts.
What is Harling? (also known as a scat coat or rough cast)
Harling is a technique for applying a coat of render or plaster. The lime mortar has extra water added to bring it to a runny consistency similiar to that of porridge. It is then cast on the wall using a special tool called a harling trowel which has a curved blade.
The harling coat provides a rough texture when cured that gives extra key for the next trowelled coat and also controls suction with very thirsty materials such as cob and brick.
Insulating Lime Renders and Plasters
A number of manufacturers now produce insulating renders and plasters. Some are based on lime putty and usually mixed with hemp and pozzolans. Others are based on hydrated lime and cement with various forms of insulation such as hemp or perlite.
Our main offering is a lightweight, dry mixture of natural hydraulic lime and cork. Being free from cement, it has good eco credentials as well as offering improved thermal performance.
ecoCORK is a product formulated exclusively with natural hydraulic lime binder and free from all cementitious content. Mixed with a largely cork aggregate, this offers a lightweight, vapour permeable and environmentally friendly render or plaster. This render is ideally decorated with SecilTEK Silicate Primer and SecilTEK Silicate Paint or a similar silicate masonry paint.
Limecrete
Limecrete is a modern interpretation of a traditional solid lime or gypsum floor that can still be seen in many historic or well preserved older homes. It has also been used to create limecrete buildings with limecrete shuttered walls.
Limecrete, known as green cement in the USA, is normally used to create an alternative to a concrete floor with or without a DPM (damp proof membrane).
It is vital to have an alternative option for a traditionally built house as an impervious, non flexible cement floor may create problems with dampness being forced into the walls at ground level which can result in poor insulation, mould growth with associated health problems and even structural damage. Many conservation officers with responsibility for listed buildings would encourage the use of the limecrete option rather than the less flexible and non-vapour permeable concrete floor buildup required by Building Regulations. The correct materials and techniques should be used on a building irrespective of whether it is listed.
Limeash were generally used on suspended timber floors onto a raft of reed and it is thought used primarily as a fire break. Limeash is sometimes used to these days to describe all lime or gypsum floors whether suspended or on a solid ground floor. These floors were originally made with lime putty and lots of a pozzolanic additives to provide an hydraulic and hard set. Although very effective, this method needs a very long time to harden and carbonate.
A Limecrete floor is made using a natural hydraulic lime powder that sets much quicker and potentially harder than the limeash floor. A mixture of NHL5 and well graded aggregates can be used to create the limecrete slab but it is also possible to introduce breathable insulation using an insulating aggregate and even underfloor heating (UFH).
For more details about limecrete, please visit our dedicated website
For more information see the information below for the materials, potential u-values and example limecrete build-ups.